Mesh reinforcement

Welded mesh sheets for a slab, allowing for laps, with the mass in kg. SANS 1024 references Ref 100 to Ref 617.

✓ Free, no sign-up ✓ Works on your phone, standing at the problem ✓ The formula and the assumptions are always shown

IT CIVILS  ·  IT ADMIN BUSTER
1 Enter the job

Mesh reinforcement

Worked out at itcivils.com/free/calculators/  ·  Free construction calculators for site teams.
Check every quantity against your own specification and your supplier's own figures before ordering.

A worked example

This is the job the page opens with, already worked out. Change any figure above and the answer changes with it.

The job

Slab length
10 m
Slab width
8 m
Layers
1
Mesh reference
Ref 193
Lap
200 mm
Sheet length
6 m
Sheet width
2.40 m
Cutting waste
5 %

The answer

7sheets  ·  Ref 193 mesh

Area to cover
80 m²
Sheet as bought
14.4 m²
Covering area after a 200 mm lap
12.76 m²
Mass per m²
3.03 kg
Total mass
305.4 kg
To order
0.305 tonnes

The working

A 6 × 2.4 m sheet lapped 200 mm covers 12.76 m².
Mass is 2 × 193 mm²/m × 7 850 kg/m³ = 3.03 kg/m².

What it assumes

All eighteen calculators

Every one has its own page, so you can bookmark the one you use most.

Concrete and masonry

Earthworks and roads

Roofing and finishes

Setting out and levels

On the job

2 Stay in the loop

Get the next tool when it lands

New tools get built when the admin gets annoying enough. Leave your email and you will hear when the next one lands. What you do on site is what decides what gets built, so it is worth saying.

Why these are free, and what they assume

These come from ten years on site: first in contracting on production and civil works, then in consulting doing construction monitoring for consultants appointed by the City of Cape Town. Working a quantity out twice, because the first answer was on a piece of board that blew away, is a thing that happens to everybody.

Every calculator shows the formula it used and the assumptions it made, because a number with no working behind it is worth nothing on site. Where a figure varies by material or supplier, it is an input you can change rather than something hidden. Check the answers against your own specification and your supplier's own figures before you order. These help you work faster, they do not replace your own judgement.

If they save you time, the paid IT Admin Buster packs cover the admin side: progress report templates, daily diaries, inspection checklists and the wording banks that go with them.